Project Description
The additional four classroom building will be located
on the existing Southern Alamance High School campus.
The program included four 900 SF classrooms, connecting
corridor, and required toilets and mechanical spaces.
|
|
Project Size
6,100 Square Feet
Student Capacity
130 Students
Construction Cost
Budget: $900,000.00
Actual: $800,000.00
Project
Schedule
Projected Months: 8
Actual Months: Under
Construction |