Project Description
This project is comprised of a classroom and auxiliary
gymnasium addition to the existing Mendenhall Middle
School.
The classroom addition contains five additional science
classrooms, a resource room, and new toilet facilities.
The Auxiliary Gymnasium addition has approximately 3,500
square feet of gym space, as well as viewing areas for
volleyball games, physical education storage, and new
accessible toilets.
|
|
Project Size
15,500 square feet
Construction Cost
Budgeted:
$2,671,800.00
Actual:
$2,370,000.00
Project
Schedule
Projected: 10 Months
Actual: 10 months |